Inspection 348898842

ATLANTIC FOOTCARE, INC.

NORTH SMITHFIELD, RI · inspection opened Friday, April 24, 2026

Citation issued
Friday, August 14, 2026
Cited items
10
Current penalty
$8,616
OSHA first proposed $17,228

First proposed is the penalty printed on the citation. Current penalty is the latest amount in OSHA's records, after any change such as a reduction in an informal settlement. Your settlement papers, if any, are the final word.

Abatement due dates

Abatement means fixing the hazard and proving the fix to OSHA.

  • Wednesday, September 30, 2026Citation 2, Item 1; Citation 2, Item 2; Citation 2, Item 3a; Citation 2, Item 3b; Citation 2, Item 4a; Citation 2, Item 4b; Citation 2, Item 5; Citation 2, Item 6
  • Friday, October 30, 2026Citation 1, Item 1; Citation 1, Item 2

Last day to contest

To contest means to formally disagree with the citation or penalty.

Likely passed on Friday, September 4, 2026

This is 15 working days after the issue date, the earliest your deadline can be. Your exact deadline counts from the day your letter arrived: use the calculator below. If the letter arrived more than 15 working days ago, the time to contest has likely passed, but fixing each item and sending proof are still due.

Cited items

Current penalty is the latest amount in OSHA's records, after any reduction. It is not a bill or an unpaid balance.

  • Citation 1, Item 1Serious

    29 CFR 1910.212(a)(1) · Machine Guarding

    First proposed
    $5,627
    Current penalty
    $2,814
    Abatement due
    Friday, October 30, 2026
  • Citation 1, Item 2Serious

    29 CFR 1910.303(g)(2)(i) · Electrical – General

    First proposed
    $5,627
    Current penalty
    $2,814
    Abatement due
    Friday, October 30, 2026
  • Citation 2, Item 1Other-than-serious

    29 CFR 1904.33(a) · Retention & Updating

    First proposed
    $1,407
    Current penalty
    $704
    Abatement due
    Wednesday, September 30, 2026
  • Citation 2, Item 2Other-than-serious

    29 CFR 1904.41(a)(1)(i) · Electronic Submission of Records

    First proposed
    $1,407
    Current penalty
    $704
    Abatement due
    Wednesday, September 30, 2026
  • Citation 2, Item 3aOther-than-serious

    29 CFR 1910.147(c)(6)(i) · Control of Hazardous Energy (Lockout/Tagout)

    First proposed
    $790
    Current penalty
    $395
    Abatement due
    Wednesday, September 30, 2026
  • Citation 2, Item 3bOther-than-serious

    29 CFR 1910.147(c)(7)(i)(b) · Control of Hazardous Energy (Lockout/Tagout)

    Proposed penalty
    Grouped with Item 3a; penalty shown there
    Abatement due
    Wednesday, September 30, 2026
  • Citation 2, Item 4aOther-than-serious

    29 CFR 1910.178(l)(4)(iii) · Powered Industrial Trucks (Forklifts)

    First proposed
    $790
    Current penalty
    $395
    Abatement due
    Wednesday, September 30, 2026
  • Citation 2, Item 4bOther-than-serious

    29 CFR 1910.178(p)(1) · Powered Industrial Trucks (Forklifts)

    Proposed penalty
    Grouped with Item 4a; penalty shown there
    Abatement due
    Wednesday, September 30, 2026
  • Citation 2, Item 5Other-than-serious

    29 CFR 1910.303(b)(2) · Electrical – General

    First proposed
    $790
    Current penalty
    $395
    Abatement due
    Wednesday, September 30, 2026
  • Citation 2, Item 6Other-than-serious

    29 CFR 1910.305(g)(1)(iv)(a) · Electrical – Wiring Methods & Components

    First proposed
    $790
    Current penalty
    $395
    Abatement due
    Wednesday, September 30, 2026

Get an abatement plan for this citation

An abatement plan lists how to fix each hazard and what proof to send OSHA. Upload the citation PDF for inspection 348898842. The free preview shows your items, owners and proof needs. You pay only after the preview.

Most cases are $349. A small case is $199. It must have all of these:

  • 1 or 2 items
  • No repeat or willful items
  • $20,000 or less in proposed penalties
  • At most 1 item that needs heavy paperwork
  • All the work goes to one owner group

You see your price before you pay.

Contest deadline calculator

15 working days to contest an OSHA citation

A federal employer has 15 working days to file a notice of contest or ask for an informal conference. Count from the day the citation arrived. Day 1 is the next working day. Saturdays, Sundays and federal holidays do not count.

Pick the date the citation arrived, not the date printed on it. Weekends and federal holidays are skipped.

OSHA Action Packet is an administrative tool. It is not legal advice and not a law firm. Talk to a lawyer before you decide whether to contest. We calculate these dates from public data and the date you enter. Check them against your own citation.